What the Board has already built
- Margin on Payments finalized, November 25, 2025 (Distribution System Code amendments, EB-2025-0083): distributors earn a 25 percent margin on payments to third-party providers of distributed energy resources used as non-wires solutions, conditional on a positive forecast net benefit, with the present value of the margin capped at half the present value of that net benefit.
- Centralized Capacity Information Map launched, January 29, 2026: a single province-wide view of load capacity and hosting capacity, updated at least quarterly.
- Flexible hosting capacity, proposed: connections beyond static feeder or substation limits where output can be varied or curtailed.
- Distribution System Operator capabilities, underway: defining what distributors need to actively manage a system with many connected resources.
- Micro-embedded generation amendments, proposed: a higher capacity limit (10 kW to 12 kW in the current proposal), removal of the commercial insurance requirement for residential customers, and improved connection impact assessment timelines.
The gap
A margin with no suppliers goes unused. Ontario's distributed solar and storage market is still largely small, local installers working project by project, so a distributor that wants a portfolio of projects at a defined location, standard, and timetable has few counterparties able to sign for it. Flexible hosting on its own is a stopgap without province-wide connection expectations, and practice still varies across roughly 60 distributors. The Board's previous strategic plan has run its course and a new plan is being drafted for 2026/27.
The proposal: three Distribution System Code amendments
- Province-wide connection timelines, with a deemed-approval backstop. Standard timelines in the Code for each stage of a connection, by size class, in every distributor's territory. Where a distributor does not respond within the timeline for a standard system using approved equipment, the application is deemed able to proceed to the next stage.
- Flexible hosting capacity as standard practice, on standard terms. The standard offer on constrained feeders, with standard curtailment terms, standard disclosure to the customer, and a standard method for estimating curtailment before connection.
- Hosting capacity data quality as a licence and reporting condition. Accuracy and currency of Centralized Capacity Information Map data as a standing reporting obligation, so the map stays a reliable planning tool.
The pilot
An Innovation Sandbox pilot with one or two willing distributors: a defined set of feeders and a portfolio of Margin on Payments eligible solar-plus-storage projects delivered by a single third-party counterparty. It would measure connection times stage by stage, curtailment actually experienced, project costs, net benefit under the Margin on Payments test, and bill impacts measured rather than estimated. Precedent: Enel X ran a 76.7 MW aggregation pilot in Ontario with $3.3 million from the IESO Grid Innovation Fund and support through the Sandbox. Every project is screened on net benefit before it is proposed, non-participating customers are held whole, and bill impact is reported in dollars per month for a typical residential customer.
The ask
- Staff-level engagement on the three amendments, including filing evidence through the Board's live consultations where that is the proper route.
- A Sandbox pilot path with a willing distributor, with the measures above agreed up front.
- That distributed energy enablement, and the connection framework that supports it, be reflected in the 2026/27 strategic plan now being drafted.
None of the three asks the Board for funding, exclusivity, or sole-source status. The software, standards, and registry approach behind this proposal are non-exclusive by design: any accredited installer can meet the standard, and any distributor can run the same pilot with another counterparty.